PCMC Building Permission Online 2026: Status & Documents
Pimpri-Chinchwad Municipal Corporation (PCMC) runs its own building-permission portal and DC rules - separate from PMC. The plot inside PCMC limits follows the PCMC timeline and fee table, not the Pune city one. Below: the 2026 process, the official BPAMS route, the documents, the fees, the realistic timelines, and the mistakes that get plans rejected on first submission.

1. PCMC jurisdiction - is your plot inside?
- Pimpri, Chinchwad, Akurdi, Nigdi, Ravet (Pawananagar fringe), Bhosari, Moshi, Dudulgaon and the older MIDC pockets
Confirm from the 7/12 - the 'महानगरपालिका' line on the extract names the authority. If it says PCMC, your permission is PCMC; if PMRDA or ग्रामपंचायत, the process differs.
2. Documents you need for a PCMC permission
- 7/12 extract (or property card for urban plots)
- sanctioned layout plan
- NA order (if your plot was agricultural and is now in PCMC limits)
- architectural drawings (site plan, all floor plans, elevations, sections) by a registered architect
- structural drawings + stability certificate
- soil test report
- the development agreement / power of attorney
- the ownership chain
PCMC's e-sanction portal uploads each as a separate PDF - keep the file sizes under 5 MB each.
3. The PCMC process, step by step
- 01Architect prepares drawings to PCMC's DC rules (setbacks, FSI, parking, height)
- 02File on the PCMC e-sanction portal (esanchar.pcmcindia.gov.in)
- 03Scrutiny at the building proposals department - expect one or two query rounds
- 04Pay scrutiny fees, development charges, premium FSI charges
- 05Sanctioned plan issued
- 06Commencement Certificate (CC) before excavation
- 07Stage inspections
- 08Occupancy Certificate (OC) at completion - required for water, power, loan and resale
4. Fees and timelines (2026)
PCMC scrutiny fees are nominal; the bigger numbers are development charges (~1.5–2% of construction cost for residential in PCMC limits) and the premium FSI charge if you exceed the base FSI. For a 1,500 sqft G+1 plot, total statutory costs are approximately ₹1.0–1.8 lakh.
Timeline for approval is 60–90 days from clean submission, though it may extend with zone or NA complications. Contrary to assumptions, PMRDA is slower than PCMC, not faster; PCMC's e-sanction system is one of the cleaner ones in the district.
5. Why PCMC permissions get rejected (the five usual reasons)
(1) FSI consumed beyond the limit on the sanctioned layout. (2) Setbacks under the DC rule - PCMC is strict on the 3m side and rear for residential. (3) Parking shortfall (1 car per 80 sqm built-up is the rule of thumb). (4) Plot access narrower than 6m. (5) Drawings inconsistent with the 7/12 or sanctioned layout. A pre-submission DC-rule check catches all five before the file is rejected - that check costs less than one query round.
6. How we run PCMC permissions
We prepare the drawings to PCMC DC rules in-house, run the pre-submission check, file on the e-sanction portal, handle the query rounds, and track the file to sanction. The PCMC cost and timeline are quoted upfront at planning - before the construction contract. Every Update Desk post on this site tracks the live PCMC circulars that change these rules.
Real questions, real answers.
How long does PCMC building permission take in 2026?
+
60–90 days from clean submission under PCMC. Faster than PMRDA but slower than most private architects expect. Delays come from document gaps or FSI/setback violations in the first drawing set.
What is the PCMC building permission fee?
+
For a 1,500 sqft G+1 plot: total statutory ~₹1.0–1.8 lakh including development charges, scrutiny fees, and any premium FSI charge. Residential development charges are ~1.5–2% of construction cost.
Can I start construction before PCMC permission?
+
No. Construction without a sanctioned plan and a Commencement Certificate is unauthorised - PCMC issues stop-work notices and MRTP-Act compounding penalties. The CC comes before excavation.
Is Ravet under PCMC or PMRDA?
+
Older Ravet (Pawananagar fringe) is PCMC; the new layouts on the eastern side are PMRDA. Confirm from the 7/12 - the authority line is the binding answer.
How do I check PCMC building permission status?
+
Use the current PCMC BPAMS or e-sanction route with your application number. The official portal shows scrutiny, query, payment and sanction stages. Your architect should track it weekly; expect a query round every 2–3 weeks.
Where is the PCMC building permission login and rules information?
+
Start with the official PCMC departments page and the BPAMS search route linked above. Portal access, forms, fee rules and circulars can change, so verify the current login and rules for your application before filing.
What is the difference between PCMC and PMRDA permission?
+
PCMC is the municipal corporation for the old twin-city limits; PMRDA is the metropolitan development authority for the Pune ring outside PMC and PCMC. Different DC rules, different fees, different timelines. PCMC is generally faster and slightly more expensive.
- PMRDA Building Permission Pune 2026: Process, Fees, Timeline & Online Portal
- NA permission, Gunthewari and 7/12 in Maharashtra: a plot owner's guide
- IGR ready reckoner and stamp duty rates for Maharashtra (2026)
- PMRDA development permission and layout approval: the 2026 process
- Baramati property tax and NOC: rates, payment and the 2026 procedure
Next step