PMRDA Development Permission and Layout Approval Process for Pune Region

PMRDA news, timelines and rule changes for Pune-region plots - for the full development permission & layout approval process, see the step-by-step 2026 guide.

4 May 2026Arsa Construction3 min read
Architectural elevation drawing - editorial visual for a building-permission update
Architectural elevation drawing - editorial visual for a building-permission update — illustrative reference for this update.

In brief

  • All residential construction on non-municipal plots in Pune district requires PMRDA building permission.
  • Plots must belong to a sanctioned layout or have valid NA (Non-Agricultural) order.
  • Online submission is processed via the PMRDA e-Challan and Building Permission scrutiny system.
  • Standard approval timeline is 30 to 45 working days with compliant architectural drawings.

Pune Metropolitan Region Development Authority (PMRDA) oversees development permissions for town and rural plots outside PMC/PCMC limits. Here is how the sanction process works.

Mandatory Documents for PMRDA Building Permission

1. 7/12 Extract (digitally signed, issued within 3 months). 2. Demarcation Map (Mojani Nakasha) from the Land Records Department (TILR). 3. Architectural Drawings (Site Plan, Floor Plans, Elevation, Section) prepared by a registered architect. 4. Structural Stability Certificate from an accredited civil engineer.

For what each column of the 7/12 actually shows - and the NA/gunthewari checks before you file - see our [7/12 land record guide](/tools/seven-twelve/) and our [NA / Gunthewari plot-verification guide](/guides/na-permission-7-12-gunthewari-guide/).

How Arsa Construction Handles Your PMRDA Sanction

When you build with Arsa Construction, our in-house planning team drafts compliant municipal drawings, pays scrutiny fees, and secures the PMRDA Commencement Certificate (CC) before construction begins.

PMRDA Sanction Milestones
StageDeliverableTypical Duration
Stage 1Mojani & Title Verification7–10 days
Stage 2Architectural Drawing & Online Filing5–7 days
Stage 3Scrutiny & Development Fee Payment15–20 days
Stage 4Commencement Certificate (CC) Issuance5–7 days

Practical tips

  • Never begin excavation on agricultural land without an NA order and PMRDA sanction.
  • Ensure the road width mentioned in the Mojani Nakasha matches the site reality.

Based on: PMRDA - Notifications & Circulars(original notice)

Share
Quick answers

Real questions, real answers.

What is the penalty for constructing without PMRDA permission?

+

Unauthorized construction may face stop-work notices, compounding penalties, or demolition orders under Section 52 of the MRTP Act. Always build with valid sanctions.