PEB warehouse, Baramati MIDC
An 8,500 sqft pre-engineered warehouse on the Bhigwan Road, built to MIDC's full sanction regime.
Plot area
9,000 sqft
Built-up
8,500 sqft shed
Duration
5 months
Spec
PEB structure

A 9,000 sqft MIDC plot, an 8,500 sqft shed, 5 months from file to handover. The structure is pre-engineered steel (PEB) with a metal deck roof, RCC foundation, and an MIDC-compliant fire and electrical spec.
We handled the MIDC NOC, the parallel BMC sanction, and the entire PEB-and-foundation coordination. The owner moved in 3 weeks before the committed date.
Cost: ₹1,150 per sqft for the PEB structure, including foundation, electrical, and the MIDC sanction cost.
What this project got right.
- ·PEB structure delivered 3 weeks ahead of schedule
- ·MIDC NOC + parallel BMC sanction, both managed in-house
- ·Fire-compliant electrical, 8,500 sqft shed
- ·Total cost ₹1,150/sqft for the PEB structure
- ·5 months from file to handover
What it was built with.
- M25 designed-mix concrete (foundation)
- Pre-engineered steel (PEB) structure
- Metal deck roof
- Fire-compliant electrical
- MIDC NOC + BMC sanction
Case-study FAQ
Real questions, from this project.
What is the cost of a PEB warehouse in Baramati MIDC?
+
For an 8,000–10,000 sqft PEB warehouse on an MIDC plot, ₹1,000–₹1,400 per sqft including foundation, electrical, and the MIDC sanction cost.
How long does an MIDC PEB warehouse take?
+
5–7 months from file to handover for a typical 8,000–10,000 sqft shed, including MIDC NOC and BMC sanction.